A Contractor Undertakes to Dig a Canal 6 Km Long

A Contractor Undertakes to Dig a Canal 6 Km Long

In 15 days, 2 km of canal are built by = `(90xx20)/15` men A contractor undertakes to dig a 6-kilometer-long canal in 35 days and employs 90 men. He notes that after 20 days, only 2 km of the canal is completed. How many men still need to be employed to complete the job on time? Geometry Webinar: Reach 90th %island geometry capacity. Number of additional men to hire to complete the job on time = 240-90 = 150 men Do you plan to complete the GMAT in 2022? Here is a micro course that will certainly help you. Start your 2022 MBA journey with Manhattan Prep`s free GMAT starter kit. Find out why Target Test Prep is the GMAT Club`s highest-rated GMAT course. Read our reviews. . Must read the article GMAT: GMAT Curriculum: The Best Way to Learn for GMAT How to Learn for GMAT While Working How to Perform Well Verbally at GMAT Learn the Meaning-Based Approach for GMAT SC Ace with Over 90% Accuracy.. .